perm filename SCHED[F,PMP] blob sn#042743 filedate 1973-05-13 generic text, type T, neo UTF8
		    WHAT IT TAKES TO FINISH FOONLY
			     13 May 1973

Design of  the Super  Foonly Processor  is complete, including  logic
drawings, printed circuit  and wirewrap cards.  Assuming that certain
parts with a  total value of  $67,500 are  donated  as expected,  the
project can be finished in about one year for the following cost.

			Personnel Costs

Salaries - 3 design engineers for 12 months,
	   plus 1 programmer for 8 months,
	   plus 1 programmer for 3 months	  $57,000

Staff benefits (17%)				    9,690

Travel - 4 East coast @$500, 10 West coast @ $100   3,000

Miscellaneous direct costs			    3,000

Indirect costs (47% of above)			   34,165

	Personnel Subtotal				     106,855


			Parts and Services

Integrated circuits
	9000 TI and other		donated
	400 AMS memory chips		 31,000
						   31,000

Printed circuit cards
	Artwork for 24 cards @ $400	  9,600
	Fabricate 163 cards of 24 types  39,600
	Stuff & solder 110 @ $20,
	    25 @ $200			  7,200
						   56,400
Wirewrap cards
	Artwork				    600
	Card fabrication 65 @ $100	  6,500
	Sockets, capacitors 55 @ $135	  7,425
	Stuff and solder 55 @ 92	  5,060
	Wiring 55 @ $146		  8,030
						   27,615
Backpanel
	2 KI-10 bays with sockets	donated
	10,000 single wires @ .10	donated
	26,000 twisted pair @ .25	donated
							0
Power supplies
	cabinet				    800
	500 Amperes @ $10 per Amp.	  5,000
						    5,800

Cooling equipment				    1,000

Card tester					    3,000

	Parts and services subtotal			      124,815

	Contingencies					       10,000

	Project total					      241,670


				SCHEDULE

Week
1	Order ICs (from DEC and AMS), PC bases for wirewrap cards
	(Vostron), power supplies (Lambda), card tester (SOTTA)

1-10	send out PC artwork.

1-13	Layout backpanel, final check of WW cards.

4-13	Artwork back, order PC cards.

4-9	Assemble card tester. Monitor fabrication processes.

10	Delivery of PC bases for wirewrap cards.

12-20	Delivery of ICs.

13-15	Order backpanel. Debug AI-DEC interface.

14-30	Make and send out paper tapes for WW cards.

15-32	Wirewrap card wrapping, stuffing, and testing (1 card per day).

16-35	PC card stuffing, soldering, and testing (2 cards/day + 2 weeks).

28	Back panel delivery.

28-35	Final assembly, including power supply instalation, cables, etc.

35-52	Processor debugging. Preliminary system work.

53-onward.  Tenex made to work on Foonly.(Minimal Foonly group
	  participation needed.)