perm filename SCHED[F,PMP] blob
sn#042743 filedate 1973-05-13 generic text, type T, neo UTF8
WHAT IT TAKES TO FINISH FOONLY
13 May 1973
Design of the Super Foonly Processor is complete, including logic
drawings, printed circuit and wirewrap cards. Assuming that certain
parts with a total value of $67,500 are donated as expected, the
project can be finished in about one year for the following cost.
Personnel Costs
Salaries - 3 design engineers for 12 months,
plus 1 programmer for 8 months,
plus 1 programmer for 3 months $57,000
Staff benefits (17%) 9,690
Travel - 4 East coast @$500, 10 West coast @ $100 3,000
Miscellaneous direct costs 3,000
Indirect costs (47% of above) 34,165
Personnel Subtotal 106,855
Parts and Services
Integrated circuits
9000 TI and other donated
400 AMS memory chips 31,000
31,000
Printed circuit cards
Artwork for 24 cards @ $400 9,600
Fabricate 163 cards of 24 types 39,600
Stuff & solder 110 @ $20,
25 @ $200 7,200
56,400
Wirewrap cards
Artwork 600
Card fabrication 65 @ $100 6,500
Sockets, capacitors 55 @ $135 7,425
Stuff and solder 55 @ 92 5,060
Wiring 55 @ $146 8,030
27,615
Backpanel
2 KI-10 bays with sockets donated
10,000 single wires @ .10 donated
26,000 twisted pair @ .25 donated
0
Power supplies
cabinet 800
500 Amperes @ $10 per Amp. 5,000
5,800
Cooling equipment 1,000
Card tester 3,000
Parts and services subtotal 124,815
Contingencies 10,000
Project total 241,670
SCHEDULE
Week
1 Order ICs (from DEC and AMS), PC bases for wirewrap cards
(Vostron), power supplies (Lambda), card tester (SOTTA)
1-10 send out PC artwork.
1-13 Layout backpanel, final check of WW cards.
4-13 Artwork back, order PC cards.
4-9 Assemble card tester. Monitor fabrication processes.
10 Delivery of PC bases for wirewrap cards.
12-20 Delivery of ICs.
13-15 Order backpanel. Debug AI-DEC interface.
14-30 Make and send out paper tapes for WW cards.
15-32 Wirewrap card wrapping, stuffing, and testing (1 card per day).
16-35 PC card stuffing, soldering, and testing (2 cards/day + 2 weeks).
28 Back panel delivery.
28-35 Final assembly, including power supply instalation, cables, etc.
35-52 Processor debugging. Preliminary system work.
53-onward. Tenex made to work on Foonly.(Minimal Foonly group
participation needed.)